Tag Archives: TRCA

Dog Zone almost ready. Nothing changes.

The new leash free zone is almost complete with a glaring exception and a puzzling oversight.

The zone looks a bit like a small horse paddock. They’re at the post…

There is no signage or anywhere to put the poop bags / cigarettes butts and coffee cups that the zone will generate. There is also some work left to ensure the fencing is well attached. Still, for a Toronto project it has been constructed relatively quickly, especially considering that two other major projects have been happening in the vicinity.

Benches are provided for owners to watch their dogs.

One major design flaw seems to be with the small dog enclosure.

An ‘airlock’ that ensures dogs don’t escape when one gate is opened.

There are two double-gated ‘airlocks’ that ensure safe entry of new dogs without allowing an unleashed dog to suddenly dart out into the park. So far so good. Unfortunately both gates lead into the large dog section.

I would have made one entrance for the large dog enclosure and a separate one for smaller dogs; but then, I’m not an expert.

The northern ‘airlock’. Note the small dog entrance some distance away accessible only from the large dog enclosure.

The long walk through the large dog section to access the small dog zone.

Unless something changes, it looks as if small dog owners will be forced to run the gauntlet through the large dog enclosure.

Some fencing still needs to be attached to the posts.

As I was taking photographs, an elderly gentleman walked by with his Jack Russell off leash, ignoring the zone. That might be a problem with this particular zone – it’s just so much nicer in the rest of the park.

Only time will tell if people will actually make use of the zone and follow the rules once they’re posted. There certainly seems to be no difference in the behaviour of many people who still come and go with their dogs off leash.

September 2016 Construction Progress Report.

The finished product - at this end anyway.

The finished product – at this end anyway.

The finished appearance of the retaining wall is now evident at its southern end with a green vegetative planting just starting to sprout on the slope at the top of the wall. Regardless, there’s still a long way to go. It also looks as if the homeowner with riparian rights has now wisely decided to take advantage of the opportunity and so construction has begun further upstream. The original intent was to construct the wall along the full length and that now seems to be the plan.

dsc05907

A nice cross-section is visible from the northern end of the wall. (click to enlarge)

Astonishingly, even after all this effort, the work looks as if it’s only about 40% done and so there is a long, long way to go before this project can be signed off. The wall construction was originally scheduled for completion this past spring with brick removal from the access area and subsequent landscaping to take place this fall. Obviously, that ain’t gonna happen. My estimate at the current rate of construction is that they’ll be lucky to have the project completed and everything restored by the end of 2017. This seems to have been quite a miscalculation by the planners. The project was to cost a maximum of $250,000.

I’ll bet that marker was skated past months ago.

Construction Progress Report

Much has been going on in Raymore Park over the summer although progress on the retaining wall seems to be slow. The dog leash enclosures are partly complete but not without controversy.

  1. The retaining wall is looking quite magnificent and it looks as if it will do the job for centuries. It looks as if the wall will be curtailed, ending before its planned end-point. This is apparently because riparian rights for the end property extend to the river and the owner feels that remediation will cause further erosion.
The wall in a completed section.

The wall in a completed section.

A view of the total wall so far.

A view of the total wall so far.

2. The off leash areas.

Two areas are being built, one for smaller dogs and one for larger breeds. One section has been built (topsoil removed, drainage completed and topped with limestone chippings).

Sadly, a sanctuary for birds and small animals has been removed to create the area. It was basically a couple of trees surrounded by dense shrubs that were impenetrable to all but small animals. It was a bit of an island or small thicket in the park but it has been removed in what seems like callous disregard for wildlife. Surely there was room to place the leash free zones without destruction of a natural resource like this?  It speaks to a lack of care for the environment and a distinct lack of planning. Let’s hope there are no more unpleasant surprises from Toronto Parks who don’t own but manage Raymore Park.

The island in from Google Earth.

The shrub island (to the right of the old baseball diamond) from Google Earth.

This thicket is no more, sacrificed for the dog enclosure.

This thicket is no more, sacrificed for the dog enclosure.

The island site shortly after its removal.

The island site shortly after its destruction.

One of the dog enclosures; further north than anticipated.

One of the dog enclosures; further north than anticipated.

More fencing and drainage pipes for the next area.

More temporary fencing and drainage pipes for the next area.

 

Not much progress

There seems to be little going on at the retaining wall site these days. It may have to do with negotiations ongoing with the owner at the north end of the wall. If the owner withholds permission for the wall to be completed on the end property, plans will need to be adjusted.

Old retaining wall blocks are stacked along the opposite shore.

Old retaining wall blocks are stacked along the opposite shore.

Part of the

The old retaining wall is being removed in preparation for a newer taller model.

Incidentally, the storm sewer pipe that is visible in the second image is one of hundreds that flow into the Humber. The structure above it may serve to prevent slope erosion.

Some Questions Answered

Work has resumed on the retaining wall and the mystery of the rope stretched across the river has been solved.

It's a lifeline.

It’s a lifeline.

It’s simply something to hang onto if a worker slips into the water accidentally.

Another question answered is what they are going to do with the old retaining wall. Answer: remove it. This week the southerly end of the old wall is being removed and workers are digging  to the bedrock to make a secure foundation for the new blocks.

Digging down to the bedrock for a solid foundation.

Digging down to the bedrock for a solid foundation.

Material being removed from the foundation of the new retaining wall.

Material being removed from the foundation of the new retaining wall.

According to a worker on the site, the work was delayed while trout were spawning but TRCA has given the project the go-ahead and construction has re-started. Apparently when the original wall was constructed, the same company simply accessed the far bank directly and never had to take all the precautions expected of projects on the river nowadays.

Another interesting item; the new wall may not extend to the northernmost point planned as the landowner above that section of wall is worried that the removal of the old blocks and subsequent digging may trigger further landslides. Since the resident in question has riparian rights which go down to the water, they have the right to withdraw consent to construct that last section of wall.

The worker allowed that the project may take until October to complete.

Retaining Wall Update April 18

At first glance nothing much seems to have changed from last week.

At first glance nothing much seems to have changed from last week.

Last week, the project took a major step forward with construction of the wall foundation to the south of the bridge. An equal length of foundation will be constructed upstream and then the wall will be added on top of that.

The retaining wall foundation stretches along its southern length.

The retaining wall foundation stretching along its southern length.

At least the question of what to do with the existing blocks is answered. They will simply be kept in place behind the new wall. With the narrowing of the existing riverbed, I wonder what the erosion implications will be on the western bank.

Retaining Wall Update March 30

Another week has gone by and progress has been made in the form of the long awaited bridge. We are now at the point (end of March) where the work was estimated to have been completed. As I have pointed out before, this is a huge undertaking. The scale of the materials and work needed to upgrade this relatively short section of retaining wall is staggering. The hard part is gaining access a long way from any roads and from the opposite bank of the river.

Panoramic shot of the bridge abutments.

A panoramic shot of the bridge abutments. The bags of gravel are to help protect the near abutment from the strong spring current.

 

The bridge with decking newly installed.

The bridge with decking newly installed. According to the orange paint, the capacity of the bridge is 27,000 lbs. I’m surprised they are still working in pounds.

 

Looking across the bridge.

A view of the bridge deck and western abutment. On the far bank, a distinct geological layer change can be seen, about a third of the way from the top. The lower grey shale layer is from the time Weston was covered by a tropical sea.

A view of the bridge from the south.

A view of the bridge from the south.

This is literally a ‘bridge to nowhere’ as the span is there to provide access to the opposite bank for the crane rather than to cross the river. Now the actual work of building the retaining wall can begin. It will be interesting to see how they go about removing the existing wall while stabilizing the slope.